AIA Billing Explained: G702, G703 and How US Contractors Get Paid

AIA billing is progress billing on standard American Institute of Architects forms. The contractor submits a G702 application for payment with a G703 continuation sheet behind it. G703 breaks the contract into schedule of values lines and shows work completed on each. G702 summarizes it, subtracts retainage and prior payments, and carries the architect’s certification.

Key facts
G702 is the application and the certificate. G703 is the line-by-line backup
G702 serves as both the contractor’s application and the architect’s certification 
The schedule of values drives the whole document. Get it right at contract signing 
Retainage is deducted on the G702, usually at 5 or 10 percent 
Subcontractor versions exist: G702S and G703S 
Most rejections are arithmetic or a change order that isn’t reflected 
AIA publishes the forms. They are licensed, not free to reproduce 

Introduction

AIA billing’s how most commercial construction in the US gets paid. It’s also where a surprising amount of cash gets stuck. The forms themselves aren’t complicated. There’s a summary page and a line-item backup. What causes trouble is everything feeding them. There’s a schedule of values written in a hurry at contract signing. Change orders approved but not added. Retainage calculated on the wrong base. This walks through what each form does, how the schedule of values drives both, and the handful of errors that cause most rejections. If you’ve had an application come back twice, the cause is almost certainly in here. 

What is AIA billing?

AIA billing means you’re submitting progress payment applications on standard forms published by the American Institute of Architects. The owner and contractor agree a contract sum. The contractor’s billing a portion of it each period, based on work completed. Rather than every project inventing its own invoice format, the AIA forms give everyone the same layout, so an architect reviewing twenty applications a month isn’t learning a new one each time.

The standard pair is the aia g702 and its G703, both in 1992 editions. There are variants. A cost-plus version. A design-build version. A construction manager edition. And a contractor to subcontractor version. One practical note. The forms are AIA products and they’re licensed, so don’t rebuild them in Excel and distribute the copy. Most ERPs that produce AIA style billing handle the licensing question for you.

What G702 and G703 each do

Two documents, two jobs. People search g702 g703 as one phrase because they always travel together. AIA Document G702 serves as both the contractor’s application and the architect’s certification. It carries the contract sum, change orders to date, total completed and stored, retainage, previous payments, and the current amount due. One page, signed and notarized. G703 is the continuation sheet. It breaks the contract sum into the individual portions of work from the schedule of values. Each line shows scheduled value, work completed previously, work completed this period, materials stored, percentage complete and the balance to finish. The relationship only runs one way. You fill in G703 first, then the totals transfer up to G702. People who fill in G702 and work backwards create the mismatches that get applications kicked back. 
For subcontractors there’s G702S and G703S, the contractor to subcontractor versions. Same mechanics, different parties. 


The schedule of values decides everything

Here’s the part that gets decided in ten minutes. Then it causes problems for two years.

The schedule of values splits the contract sum into billable lines

AIA hasn’t published a standard form for it. The contractor prepares it, the architect approves it, and from then on it governs every application you submit.

Too few lines and you can’t bill accurately

One $2M line for mechanical means arguing about a percentage every month. Too many lines and the architect’s reviewing 300 rows, which slows approval.

Front loading’s the other issue

Weighting early lines high to help cash flow is common and most architects watch for it. Get caught and your applications get scrutinized for the rest of the job.

Our view, and it’s a mild opinion

Build the schedule of values from your cost code structure, not separately. When the two match, your billing and your job cost report finally agree, and the WIP conversation gets a lot shorter.


Filling out a pay application, line by line

Start on G703

Column A the line number, column B the description, column C the scheduled value. Those three come straight from the approved schedule of values and shouldn’t change.

Record work completed

Column D is work completed in previous applications. Column E is this period. Together they give total completed, which drives the percentage.

Add stored materials

Column F covers materials on site but not yet installed. Owners often want proof of delivery and insurance before paying it, so check the contract.

Carry the totals to G702

Total completed and stored goes to line 4. Retainage comes off at the contract rate on line 5. Previous certificates come off on line 6. What’s left is the current payment due.

Reconcile change orders

G702 has a change order summary block. Approved changes have to be in both the summary and the relevant G703 line. Our post on change order management covers why that link breaks.

Attach the waivers

Conditional lien waiver with the application, unconditional once paid. The lien waiver guide sets out the sequence.


Why AIA billing gets rejected

Five reasons cover most of it. Four are avoidable.

Arithmetic that doesn’t tie. The G703 totals don’t match the G702 summary. That’s the most common rejection and it’s entirely a systems problem.

Change orders missing from a line. The change got approved, the contract sum on G702 went up, but the G703 line still shows the original value. Now nothing reconciles.

Percentage disputed. You’ve claimed 70 percent, the architect’s walked the job and says 55. This one’s a real disagreement rather than an error, and it’s why photographic backup is worth attaching. 

Retainage on the wrong base. Plenty of contracts drop the rate after 50 percent completion. Keep billing 10 percent after the step-down and you’re holding money you’re not entitled to hold. 

Missing waivers or expired insurance. The numbers are right and the application’s still sits, because the compliance file isn’t current.


AIA billing software and what to look for

Most construction ERPs produce AIA style applications. Quality varies. It varies a lot more than the marketing suggests. Four things to test in a demo, on your own contract. Does the schedule of values live as a record that drives billing, or is it re-keyed each period? Do approved change orders flow onto the right G703 line automatically? Does retainage handle a step-down rate? And does the output actually look like a G702, or is it an export to a template?

NetSuite’s construction ERP prepares payment applications using verified progress, approved changes and retainage terms, with a person reviewing before posting. Acumatica covers progress billing and change orders in the construction edition. Sage Intacct, Sage 300 CRE, Foundation and CMiC all produce AIA style billing too. If you’re evaluating standalone AIA billing software, the question is what happens to the data afterwards. A tool that produces a beautiful G702 and doesn’t post to your ledger has moved the rekeying rather than removed it. Our construction reporting work usually starts by finding where that re-entry happens.


Why work with Proxsoft

Proxsoft is a multi-ERP construction technology firm. We work across Acumatica, NetSuite, Sage Intacct, Business Central, QuickBooks and Intuit Enterprise Suite, Procore, Primavera P6, Sage 300 CRE, CMiC and Foundation. Billing problems usually aren’t billing problems. It’s a schedule of values that doesn’t match the cost codes, or change orders that live in email. We fix the structure first, then the forms come out right on their own. Our construction accounting team handles the process, and our construction ERP consultants handle the configuration so applications tie on the first submission. 


Frequently Asked Questions


Conclusion

AIA billing is mechanical once the inputs are right. G703 holds the detail, G702 summarizes it, and the schedule of values governs both. Spend the time on the schedule of values at contract signing, and build it from your cost codes so billing and job cost agree. Then keep change orders flowing onto the lines they belong to. Do those two things and most rejections stop happening. If your applications regularly come back, talk to the Proxsoft team and bring the last one that got rejected.